To supply the town of Belgrade with water, the purification plant "Makis" was designed and constructed to process the Sava river water into drinking water.
Detail design:
Energoprojekt
Sub-contractor:
Energoprojekt, Mostogradnja, Ratko Mitrovic, Janko Lisjak
Designer:
V. Misita, Energoprojekt, B. Petrovic
§ The first stage is of the capacity 2 m3/s. On the basis of the technological treatment process, the plant consists of the following individual structural units: input structure, raw water pumping station "Sava", divisional pool, pre-treatment and clearing, ozonization, filter service building, pure water reservoir, pure watt pumping station, aerator, mud treatment, chemical building, pumping station for balancing reservoir re-circulation, control-laboratory centre.
§ In order to meet very strict functional requirements due to non-uniform subsidence, the main structures of the filter line, clearing and ozone filters, were founded on the "Franci" piles dia 520 mm, length 15 m.