Project Details PRINT PDF

The Rzav regional water supply system

Raw water tapping from the water intake on the Rzav river and transport to the water treatment plant.


  • Employer: Public Co. "Rzav"
  • Location: Rzav
  • Total cost of project: N/A
  • Years of construction: 1988 - 1993
  • Category: Hydro-Engineering Projects
  • Status: Finished
  • Area: Unknown
  • Contractor: Ratko Mitrovic, Janko Lisjak

Detail design:
Institute for Water Management "Jaroslav Cerni"

Sub-contractor:
Jedinstvo, Novi Kolektiv, Gradjevinar, Progres

Designer:
Mihajlo Radosavljevic, Sonja Pavlovic, Dragan Zdravkovic, Dejan Divac

Photo Gallery

Information

Raw water purification up to the drinking water quality and pure water distribution in five directions (gravitational pipeline to 4 consumers and displacement pipeline to one consumer).

§ Temporary water intake of raw water - raw water pipeline Ø 1,200 mm and raw water pumping station capacity Q = 1,300 1/s; water treatment plant capacity Q = 1,300 1/s (pre-chlorination, coagulation, flocculation, sedimentation, ozonization, filtration, disinfection, fluoridation); pure water pipelines: reinforced concrete pipelines Ø 1,200 mm, Ø 1,000 mm and Ø 800 mm, in the length of 20,300 m; steel pipelines Ø 1,100, Ø 1,000, Ø 800, Ø 500 and Ø 600 mm in the length of 50,500 m, and cast iron pipelines Ø 500 and Ø 300 in the length of 500 m.


Press clipping

  • There is no press clipping for this project